To behave ALMOST like P3/P6 on this you need to set some options.
MS project 2010:
File - Options - Advanced - Calculation Options For This Project
Move end of completed parts after status date back to status date (not like P3/6 but you need to set this one to yes, otherwise you cannot select the next one) YES
and move start of remaining parts back to status date (like P3/P6 standard) YES
Move start of remaining parts before status date forward to status date (like P3/P6 standard) YES
and move end of completed parts forward to status date (not like P3/P6, so optional for you) ?
Once you have set these options, you can schedule thr project with
Project - Update Project - Reschedule uncompleted work to start after (type in status date)
These settings will make any project planner who moved from P3/6 ro MS Project very happy.
To behave ALMOST like P3/P6 on this you need to set some options.
MS project 2010:
File - Options - Advanced - Calculation Options For This Project
Move end of completed parts after status date back to status date (not like P3/6 but you need to set this one to yes, otherwise you cannot select the next one) YES
and move start of remaining parts back to status date (like P3/P6 standard) YES
Move start of remaining parts before status date forward to status date (like P3/P6 standard) YES
and move end of completed parts forward to status date (not like P3/P6, so optional for you) ?
Once you have set these options, you can schedule thr project with
Project - Update Project - Reschedule uncompleted work to start after (type in status date)
These settings will make any project planner who moved from P3/6 ro MS Project very happy.
I need to know the status of any project on some earlier dates. I tried changing status date. The mode of calculation was set to automatic. There were no changes observed. I was not able to get the % complete of each task as on the status date. Is there any way to get all details of my project as on a particular Date..
Thanks & Regards
Member for
19 years 11 months
Member for19 years11 months
Submitted by Trevor Rabey on Wed, 2010-01-13 05:53
The reason MSP does not do anything automatically just because you set a status date is because it is waiting for you to tell it what happened. It doesnt have eyes or legs and it cannot go to the site and have a look at the job and it cannot read the site records, but you can. Only you know if the task has started and when. Only you know whether the task has been in progress continuously up to the status date, or whether it was interrupted, or what the actual duration is, or what the actual finish date was if the task is finished, or what the remaining duration estimate is.
This general idea is as applicable for P3 as it is for MSP.
If you have been actualising tasks in P3 with one click of a button you have been allowing or forcing the software to make a lot of assumptions which are probably not correct.
Member for
19 years 11 months
Member for19 years11 months
Submitted by Trevor Rabey on Wed, 2010-01-13 05:46
Have the Tracking Toolbar visible/available (View, Toolbars etc).
Switch to the Tracking Gantt View.
Switch to the Tracking Table (View, Table etc).
Make the Status Date vertical red line in the tracking gantt chart (Format Gridlines).
Select the task that you are interested in.
Click the 2nd button from the left on the Tracking Toolbar.
That will do for now but there is a bit more to it if the task actual start date, actual duration and actual finish date are not the same as planned, or if the task was not continuously in progress up to the status date, or if the actual work or actual cost are not as planned.
Let us know how you get on up to this point.
BTW, I have described this simple and effective procedure about 1000 times, often with more detailed explanation, both here and at the newsgroup microsoft.public.project.
Member for
13 years 3 monthsTo behave ALMOST like P3/P6
To behave ALMOST like P3/P6 on this you need to set some options.
MS project 2010:
File - Options - Advanced - Calculation Options For This Project
Once you have set these options, you can schedule thr project with
Project - Update Project - Reschedule uncompleted work to start after (type in status date)
These settings will make any project planner who moved from P3/6 ro MS Project very happy.
Member for
13 years 3 monthsTo behave ALMOST like P3/P6
To behave ALMOST like P3/P6 on this you need to set some options.
MS project 2010:
File - Options - Advanced - Calculation Options For This Project
Once you have set these options, you can schedule thr project with
Project - Update Project - Reschedule uncompleted work to start after (type in status date)
These settings will make any project planner who moved from P3/6 ro MS Project very happy.
Member for
14 yearsHi everybody.. I need to know
Hi everybody..
I need to know the status of any project on some earlier dates. I tried changing status date. The mode of calculation was set to automatic. There were no changes observed. I was not able to get the % complete of each task as on the status date. Is there any way to get all details of my project as on a particular Date..
Thanks & Regards
Member for
19 years 11 monthsRE: Status date in Microsoft Project
The reason MSP does not do anything automatically just because you set a status date is because it is waiting for you to tell it what happened. It doesnt have eyes or legs and it cannot go to the site and have a look at the job and it cannot read the site records, but you can. Only you know if the task has started and when. Only you know whether the task has been in progress continuously up to the status date, or whether it was interrupted, or what the actual duration is, or what the actual finish date was if the task is finished, or what the remaining duration estimate is.
This general idea is as applicable for P3 as it is for MSP.
If you have been actualising tasks in P3 with one click of a button you have been allowing or forcing the software to make a lot of assumptions which are probably not correct.
Member for
19 years 11 monthsRE: Status date in Microsoft Project
Set the Status Date, as you have done.
Set a Baseline (Tools, Tracking, Baseline)
Have the Tracking Toolbar visible/available (View, Toolbars etc).
Switch to the Tracking Gantt View.
Switch to the Tracking Table (View, Table etc).
Make the Status Date vertical red line in the tracking gantt chart (Format Gridlines).
Select the task that you are interested in.
Click the 2nd button from the left on the Tracking Toolbar.
That will do for now but there is a bit more to it if the task actual start date, actual duration and actual finish date are not the same as planned, or if the task was not continuously in progress up to the status date, or if the actual work or actual cost are not as planned.
Let us know how you get on up to this point.
BTW, I have described this simple and effective procedure about 1000 times, often with more detailed explanation, both here and at the newsgroup microsoft.public.project.
Try a search.
Member for
18 years 3 monthsRE: Status date in Microsoft Project
hi
try this
tools - tracking update task
and
tools - tracking update project