Primavera Project Planner - P3 Member for 20 years 1 month Member for 20 years 1 month Submitted by Shareef Abdul Azeez on Wed, 2010-01-06 01:19 Permalink RE: Suspend & Resume Hi thanx for your reply. I would lke to know what would happen if I donot use suspend and resume for an activity which has actually been suspended coz of some obstructions. I think it will affect the costing part in P3. or may be the remaining duration. Am I right? Member for 17 years Member for 17 years Submitted by harzelli bouasria on Mon, 2010-01-04 10:30 Permalink RE: Suspend & Resume Hi you have the choice: 1. if you dont know resume date, let it open 2. else you nmust put the suspend and resume date good luck Log in or register to post comments
Member for 20 years 1 month Member for 20 years 1 month Submitted by Shareef Abdul Azeez on Wed, 2010-01-06 01:19 Permalink RE: Suspend & Resume Hi thanx for your reply. I would lke to know what would happen if I donot use suspend and resume for an activity which has actually been suspended coz of some obstructions. I think it will affect the costing part in P3. or may be the remaining duration. Am I right?
Member for 17 years Member for 17 years Submitted by harzelli bouasria on Mon, 2010-01-04 10:30 Permalink RE: Suspend & Resume Hi you have the choice: 1. if you dont know resume date, let it open 2. else you nmust put the suspend and resume date good luck
Member for
20 years 1 monthRE: Suspend & Resume
Hi
thanx for your reply.
I would lke to know what would happen if I donot use suspend and resume for an activity which has actually been suspended coz of some obstructions.
I think it will affect the costing part in P3. or may be the remaining duration.
Am I right?
Member for
17 yearsRE: Suspend & Resume
Hi
you have the choice:
1. if you dont know resume date, let it open
2. else you nmust put the suspend and resume date
good luck