Duration

Member for

16 years 11 months

hi

check this formula ,i thrust it would be useful to you



Driving Resource Duration = Quantity to complete / units per time period

Member for

18 years 8 months

1- You need to estimate the Qty. for each resource assigned to the activity



2-Find the average productivity for each



3- Specify the availability for each resource



4- Mark the driven resources



Then the biggest duration will be considered, which is already calculated as a result for the steps 1-4 above

Member for

16 years

could you explain me, the method please

Member for

18 years 8 months

Yes of course