DONT! Do not delete any of the 23 files that share the same first 4 letters and have each of the last 3 letters you call "extension".
A P3 project is stored in these 23 files whose name begins with the 4 letters or digits of the project name you have keyed in in the New Project dialog box; I am not sure of all the 3 letters, I willonly give some examples: CAL = list of calendars, HOL = list of days off in the calendars, WBS = Work Breakdown Structure, LAY = list of layouts, ... S50 = administrative file containing the user ID.
Member for
21 years 9 monthsRE: Regarding the File extension in the P3 folder.
So maybe you discufer a way to manipulate data quicker?
Member for
16 years 11 monthsRE: Regarding the File extension in the P3 folder.
Quite interesting ,where they have been used i mean in global change ?
Member for
16 years 4 monthsRE: Regarding the File extension in the P3 folder.
Thanks a lot,
Regards
Anbin Ponnith
Member for
18 years 5 monthsRE: Regarding the File extension in the P3 folder.
I hope, this is what u r looking for:
ACT Activities Table
REL Relationships Table
LOG Log records Table
WBS Assignments Table
SRT Current sort Table
AIT Read Only Activity custom data items Table
RES Resource assignments Table
STR WBS Structure Table
ACC Cost Accounts Table
RLB Resource dictionary Table
RIT Read Only Resource custom data items Table
DTL Read Only Activity code titles/values Table
HOL Holiday file Table
TTL Title descriptions
DIR General project information Table
SPR Resource cost/spread table
ITM Data in dictionary records
CAL Calendar definition file
REP Resource earned value
AC2 Restricted access records
LAY Project layouts
STW Communicates with SureTrak program
Cheers,
Member for
22 years 9 monthsRE: Regarding the File extension in the P3 folder.
Anbin,
DONT! Do not delete any of the 23 files that share the same first 4 letters and have each of the last 3 letters you call "extension".
A P3 project is stored in these 23 files whose name begins with the 4 letters or digits of the project name you have keyed in in the New Project dialog box; I am not sure of all the 3 letters, I willonly give some examples: CAL = list of calendars, HOL = list of days off in the calendars, WBS = Work Breakdown Structure, LAY = list of layouts, ... S50 = administrative file containing the user ID.
HTH, Alexandre