You can do it with the help of custom data items and global change
1 . Use custom data item select activity tab and assign AQ and character as precision
2. Use global change and select the resource whose BQ to be changed and apply conditions as shown
If RES EQ ENG
THEN AQ EQ BQ * 1.1 (any Multiplier to reflect your need )
I hope you can use these value in report it will not affect your baseline what ever you do in custom item and storing it in custom data will not affect your schedule
Member for
16 years 11 monthsRE: Input Actual Quantity Resource
You can do it with the help of custom data items and global change
1 . Use custom data item select activity tab and assign AQ and character as precision
2. Use global change and select the resource whose BQ to be changed and apply conditions as shown
If RES EQ ENG
THEN AQ EQ BQ * 1.1 (any Multiplier to reflect your need )
I hope you can use these value in report it will not affect your baseline what ever you do in custom item and storing it in custom data will not affect your schedule