a) the activity type: Task = Duration and activity calendar, Independant = Duration and assigned resources calendars, Meeting = Duration and workperiods where all the assigned resources are working at the same time
b) is the resource driving or not? Driving = Resource, not driving = Duration
Member for
16 years 11 monthsRE: Scheduling issue
Thanks Mr.Alexandre
Member for
22 years 9 monthsRE: Scheduling issue
Shahul,
the result depends on:
a) the activity type: Task = Duration and activity calendar, Independant = Duration and assigned resources calendars, Meeting = Duration and workperiods where all the assigned resources are working at the same time
b) is the resource driving or not? Driving = Resource, not driving = Duration
I hope it helps,
Alexandre