Dates aligning incorrect

Member for

17 years 2 months

Thanks Guys,



I have sorted it out

The working times were 8 till 5 but the calender was 7 till 5

The extra hour was pushing the tasks over to the next day



Thanks david & nicolas

Member for

18 years 4 months

Hi Andrew



Check that

1) duration of day

in Tools Options Calendar

is compatible with

2) dayly working time

in Tools Modify working time.



If you tell MSP

that

1) your "day" is 10 hours long

but

2) you allow only 8-12am and 2-6pm you will need

finish the next day.



hth

Member for

17 years 2 months

Trying to "fill down"to make my start times all 7 am but wont let me make the changes.

aaaahhhrrrr

Member for

17 years 2 months



Great idea



I have found the problem in the start times are all over the place, but my calender starts at 7 and finishes at 5 every day

The same calender is assigned to all tasks.

Ill keep digging


Member for

20 years 5 months

could be down to the time also, when does the working day start, etc.



expand the start and finish columns so that you see the start date and time and the finish date and time (you might need to format how the date is viewed).



D.

Member for

17 years 2 months



Working days are set to 8hr days



I figure it has something to do with the calender day anfd hrs but cant put me finger on it!

Member for

20 years 5 months

how long are your days?



silly question, but if you’re calendar is 24 hours and you start something at 8am on the 12th, the finish will be 7.59am on the 13th. If your calendar is working hours/days, your duration ’should’ (theoretically) be 8 hours, so, start and finish on same date, duration = 1 day.



try putting your duration down as 8 hours.



D.