Primavera Project Planner - P3 Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Wed, 2009-08-05 16:47 Permalink RE: Relationship Between Activities Hi Irfan In other words you cannot paint a wall until it has been plastered. Its that simple - and yet again it is that complex. Best regards Mike Testro. Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Wed, 2009-08-05 13:57 Permalink RE: Relationship Between Activities Irfan, the predecessor is the task you HAVE to complete before you can start another task the successor is the task you cannot start before another task is complete Alexandre Log in or register to post comments
Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Wed, 2009-08-05 16:47 Permalink RE: Relationship Between Activities Hi Irfan In other words you cannot paint a wall until it has been plastered. Its that simple - and yet again it is that complex. Best regards Mike Testro.
Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Wed, 2009-08-05 13:57 Permalink RE: Relationship Between Activities Irfan, the predecessor is the task you HAVE to complete before you can start another task the successor is the task you cannot start before another task is complete Alexandre
Member for
19 years 10 monthsRE: Relationship Between Activities
Hi Irfan
In other words you cannot paint a wall until it has been plastered.
Its that simple - and yet again it is that complex.
Best regards
Mike Testro.
Member for
22 years 9 monthsRE: Relationship Between Activities
Irfan,
the predecessor is the task you HAVE to complete before you can start another task
the successor is the task you cannot start before another task is complete
Alexandre