Project BaseLine

Member for

19 years 11 months

If you just want to compare the baseline start and finish from another (older) file with the current start and finish in the newer file you can just copy and paste the baseline start and baseline finish fields from the older and paste them into corresponding fields in the newer file.

This assumes that you still have the same number of tasks in the same arrangement with the same ID numbers in both files, but even if not it is still easy with a bit of help from filters etc.

Member for

23 years 4 months

I am still use 2003 version. I have already tried your sugestion. thanks

Member for

22 years 9 months

Berli_,

which MS Project are you using? in MSP 2007 and if I remember well with 2003 too, go to View, Toolbars, and display the "Compare projects" bar (or something equivalent, as I am translating from the French

Alexandre

Member for

23 years 4 months

Alex,

Thanks for your input, so MS.Project can not import a baseline from other file. My problem is I want to compare the current schedule with one of my scenario when developed the schedule. thanks

Member for

22 years 9 months

Berli_

in MS Project, baseline is part of the current projet;

Click Tools, Tracking, Save baseline (Define baseline in MSP2007)