constraints

Member for

17 years 4 months

thanks steve



got the job done

Member for

17 years 1 month

In MS Project 2003 (it’s probably similar in 2007) there’s an option in Tools->Options->Scheduling called ’New tasks:’, which you can configure to the current date or the project start date. Of course ideally every task in your schedule should be linked to a predecessor.



When constructing a schedule from scratch is it often useful to create a milestone called ’Project Baseline Start’ with an ’Actual Finish’ set to the current date. This can be linked to any tasks that are due to start immediately.



Cheerio...

Steve

Member for

19 years 10 months

Hi Faisal



Sorry but I have no further suggestions to offer.



Best regards



Mike Testro

Member for

17 years 4 months

rather than your sympathy i would honour your suggestion please

Member for

19 years 10 months

Hi Faisal



I hate Microsoft Project and never use it unless I have to.



You can - I beleive - do a global search and constraint removal.



There is also a default setting somewhere that sets the attributes for new activities - the standard is to put a constraint on every activity - just plain bonkers.



You have my deepest sympathy having to use such rubbish.



Best regards



Mike Testro.