can I put RD > OD in P3 !

Member for

22 years 9 months

Mimoune yâ khô,

P3 computes Pct to be equal to (OD-RD)/OD and not under 0; therefore, when you enter RD > OD, Pct becomes 0; should you have OD = 3, RD = 4, "new scheduled duration" = 7, you will enter Pct accordingly

Have a good time in Arzew, I am going back to Paris and be in Algiers again within one month inch’allah

Alexandre

Member for

19 years

escander yeah my friend, i am always in arzew, now it become very interesting, many nationalities, we lack only people from Antarctica.



Joao Reibero, yes of course, this option is off, otherwise i can’t get P3 to show me, RD> OD



Please can you take a look at this thread and tell me what you think !!



http://www.planningplanet.com/forum/forum_post.asp?fid=&Cat=1&Top=58911…



thanks very much

Member for

22 years 7 months

Have you checked the options "Link remainig duration and schedule percent complete" and the ones for summarization?



HTH

Member for

22 years 9 months

saha mimoune, ouash rak?

I just faced the same situation today while giving a training session on P3 in Hydra

I have entered the total percent complete by hand in the Pct field

is Arzew still fine for you?

Alexandre ’iskander el dziri’