Help with Schedule Finish Dates

Member for

16 years 7 months

I don’t have the software no this computer, so donig this from memory:



On the time now advanced settings, there should be an option called something like "actual dates overide logic". If that option isn’t enabled, I think out of sequence progress can cause issues like you describe.



HTH