Unmerge Projects

Member for

17 years 5 months

Dear Ernani,



I am going to write what i will do. Please feel free to use another methods:



-Create a new project, transfer all data about calendar, activity codes, project codes & resource codes(All dictionary) from existing file.

-I assume that you will have at least one activity code that you can seperate this subprojects.

-Use export and import to create subprojects.

-Tools-Project Utilities-Export from your main schedule.

-Add an export name as activity information

-Select all current and from format tab select the name and file type (I use .dbf because it is user friendly w/excel)

-Add an export name as relations

-Select successor relationships and from format tab select the name and file type (I use .dbf because it is user friendly w/excel)

-You will have 2 dbf files that includes all info about your schedule

-COPY the activity information .dbf as the number of subprojects you will use.

-For each subprojects delete the other projects activity information in .dbf by filtering the approtiate activity codes.

-Start producing Subprojects in your master schedule.

-For each of subproject import (Tools-Project Utilities-Import) associated .dbf files (one for activity info one for relations)

-After completing all subprojects you can transfer all reports layouts from your main schedule.

-You can seperate the project into subproject within hours but at last you will need to check every activity and relations one by one in order to avoid any miss.



****You must not use Data-Activity Codes-Activity ID(TAB)-Subproject, as a identicator of subproject in you activity id. You can add other activity codes in the process by creating in new project and copy to .dbf



Sorry for language fast-writing and no time to relook.



Regards,



Safak