There are other options that are needed to be decided at the beginning of planning process.The autocost rules purely determines the all mentality.
If you are monitoring directly Earned Value from P3. Then I recommend you to use default options in Autocost rules. If you change the autocost rules, original durations, resources then you will have inproper variances. There are mitigations
for this:
-You need to update remaining duration, %, QTC or QAT manually (Or import-export from excel to be faster(macro difference)) at every update.
-You can remove the aotocost rules that autocalculates resoruces with %. You can update this datas manually also.
The most important aspect is that all of the changes that we are talking will be rejected by CLIENT. They want a clear CP and the updated programme which is same as the baseline (The reason can be contractual or only as procedures).
I can understand that they also want to see realistic lookaheads and end-dates in order to get decisions.
I have another suggestion that your CLIENT can approve. The important point about the schedule will be end-dates not %. So you can change your activities end dates with extra&dummy relations or constraints to achieve those end dates. You need to record all this extra relationships and report them.
Sorry for long thread. I will be happy if this thread gives opinion.
Post #1 - Some activities will give less Look Ahead % compared to Present % Complete because P3 calculates % to complete based on remaining duration...
If you progressed this week ahead of your previous week look-ahead plan, then definitely youll have less % previous look-ahead % complete. Theres no relation between them during normal P3 calculations, except if you use GC options.
Kafo is right on his Post # 2 (basic P3 stuffs).
We normally use look-ahead schedules for reporting purposes to check periodically whether we are progressing as per current plan, and what its periodic impact on the overall baseline schedule more importantly if the project is delayed.
Cheers,
R. Catalan
Member for
17 years 7 months
Member for17 years7 months
Submitted by Adekunle Arisilejoye on Tue, 2009-03-17 06:47
If I will follow your advise (if I understood it correctly), The result will give schedule variance... I tried many possibilities but I failed... But I will still check your advise.
Thnx and more power,
Francis
Member for
16 years 8 months
Member for16 years8 months
Submitted by Francis Aborot on Fri, 2009-03-13 08:32
Thats the story is all about, I cannot link the remaining duration with percent complete. Why? Because the realistic remaining duration of the activity in the site is different from the theoretical remaining duration in P3...
You shall find a box ticked that says "Link Remaining Duration and Schedule Percent complete"
Untick this box and you are ste to go
--> Note if you go to this option you have to update all 4 variables at each activity : i.e Actual Start , Actual Finish , % Complete & Remnaining Duration
Meaning that RD will not be calculated anymore and you have to estimate the Remaining days to go on each activity based on site conditions
Member for
17 years 5 monthsRE: LOOK AHEAD SCHEDULE
Dear Francis,
There are other options that are needed to be decided at the beginning of planning process.The autocost rules purely determines the all mentality.
If you are monitoring directly Earned Value from P3. Then I recommend you to use default options in Autocost rules. If you change the autocost rules, original durations, resources then you will have inproper variances. There are mitigations
for this:
-You need to update remaining duration, %, QTC or QAT manually (Or import-export from excel to be faster(macro difference)) at every update.
-You can remove the aotocost rules that autocalculates resoruces with %. You can update this datas manually also.
The most important aspect is that all of the changes that we are talking will be rejected by CLIENT. They want a clear CP and the updated programme which is same as the baseline (The reason can be contractual or only as procedures).
I can understand that they also want to see realistic lookaheads and end-dates in order to get decisions.
I have another suggestion that your CLIENT can approve. The important point about the schedule will be end-dates not %. So you can change your activities end dates with extra&dummy relations or constraints to achieve those end dates. You need to record all this extra relationships and report them.
Sorry for long thread. I will be happy if this thread gives opinion.
Regards,
Safak
Member for
20 years 2 monthsRE: LOOK AHEAD SCHEDULE
Francis,
Post #1 - Some activities will give less Look Ahead % compared to Present % Complete because P3 calculates % to complete based on remaining duration...
If you progressed this week ahead of your previous week look-ahead plan, then definitely youll have less % previous look-ahead % complete. Theres no relation between them during normal P3 calculations, except if you use GC options.
Kafo is right on his Post # 2 (basic P3 stuffs).
We normally use look-ahead schedules for reporting purposes to check periodically whether we are progressing as per current plan, and what its periodic impact on the overall baseline schedule more importantly if the project is delayed.
Cheers,
R. Catalan
Member for
17 years 7 monthsRE: LOOK AHEAD SCHEDULE
Francis,
Could you explain hw u performed the following
2. Previous Look Ahead%
4. New Look Ahead %
Cheers
K
Member for
16 years 8 monthsRE: LOOK AHEAD SCHEDULE
Dear Francis
Based on your req. I think the solution I gave you is what you are looking for
Tell me how did you go
Cheers
Member for
16 years 8 monthsRE: LOOK AHEAD SCHEDULE
Hi Kafo,
If I will follow your advise (if I understood it correctly), The result will give schedule variance... I tried many possibilities but I failed... But I will still check your advise.
Thnx and more power,
Francis
Member for
16 years 8 monthsRE: LOOK AHEAD SCHEDULE
Hi Kafo,
Thats the story is all about, I cannot link the remaining duration with percent complete. Why? Because the realistic remaining duration of the activity in the site is different from the theoretical remaining duration in P3...
Other ideas please...
Thnx and more power,
Francis
Member for
16 years 8 monthsRE: LOOK AHEAD SCHEDULE
From P2 --> P3e
Go To Tools --> Options --> Autocost Rules
You shall find a box ticked that says "Link Remaining Duration and Schedule Percent complete"
Untick this box and you are ste to go
--> Note if you go to this option you have to update all 4 variables at each activity : i.e Actual Start , Actual Finish , % Complete & Remnaining Duration
Meaning that RD will not be calculated anymore and you have to estimate the Remaining days to go on each activity based on site conditions
Hope this answers your query