incomes Vs cost for the BoQ items

Member for

20 years 2 months

Mario,



A) Use the BOQ Selling cost-loaded schedule for reporting purposes to Client/Engineer. On this schedule, you can show periodic schedule variance analysis reports, e.g, Planned Value (BCWS) vs. Earned Value (BCWP). If you find it hard doing in P3/P6, you can extract P3/P6 values and do the exercise in Excel (Again!).



BCWS = BAC x Planned % C

BCWP = BAC x Actual % C

BAC = You can use your Contract BOQ as your BAC

SV = BCWP (EV) - BCWS (PV)



B)Copy the schedule in (A) and load periodic actual cost. You can now complete your variance analysis for your internal reporting requirements.



Add to the above:

CV = BCWP (EV) - Actual Cost



Hope this helps.



R. Catalan

Member for

17 years 3 months

Hi,



Your are talking about the Cost that is related to the Resources; Raw Material, Manpower and Equipment.



Each resource can have an associated cost with it. You can manage your cost accordingly.



Best Regards,



Samer