Primavera Project Planner - P3 Member for 16 years 9 months Member for 16 years 10 months Submitted by Sam Abbitt on Fri, 2009-01-16 14:23 Permalink RE: How to Move Date Sight Line? Thanks everyone. Member for 18 years 5 months Member for 18 years 5 months Submitted by Sajid Balma on Fri, 2009-01-16 10:48 Permalink RE: How to Move Date Sight Line? 1. Click Data 2. Click Calendars... 3. Click Global Calendar 4. Click Standard... 5. Select a new date under Data Date Close windows Now your schedule has new sight line as per your new data date without any change in the schedule. TAAAADAAAA Member for 16 years 9 months Member for 16 years 10 months Submitted by Sam Abbitt on Fri, 2009-01-16 09:32 Permalink RE: How to Move Date Sight Line? Not sure why, but when I go to copy the schedule it keeps telling me "Invalid Project Name". Any ideas? Member for 18 years 9 months Member for 18 years 9 months Submitted by Jean-Philippe … on Fri, 2009-01-16 05:39 Permalink RE: How to Move Date Sight Line? Hi Sam, If it is only for printing, a turnaround for your problem may be: (Make backups before !) - Make a copy of your schedule, - Set the copy as a target for your schedule. - Update the data date of the current schedule - In the bar chart, hide all the bars but the Target Bar. Hope this helps Log in or register to post comments
Member for 16 years 9 months Member for 16 years 10 months Submitted by Sam Abbitt on Fri, 2009-01-16 14:23 Permalink RE: How to Move Date Sight Line? Thanks everyone.
Member for 18 years 5 months Member for 18 years 5 months Submitted by Sajid Balma on Fri, 2009-01-16 10:48 Permalink RE: How to Move Date Sight Line? 1. Click Data 2. Click Calendars... 3. Click Global Calendar 4. Click Standard... 5. Select a new date under Data Date Close windows Now your schedule has new sight line as per your new data date without any change in the schedule. TAAAADAAAA
Member for 16 years 9 months Member for 16 years 10 months Submitted by Sam Abbitt on Fri, 2009-01-16 09:32 Permalink RE: How to Move Date Sight Line? Not sure why, but when I go to copy the schedule it keeps telling me "Invalid Project Name". Any ideas?
Member for 18 years 9 months Member for 18 years 9 months Submitted by Jean-Philippe … on Fri, 2009-01-16 05:39 Permalink RE: How to Move Date Sight Line? Hi Sam, If it is only for printing, a turnaround for your problem may be: (Make backups before !) - Make a copy of your schedule, - Set the copy as a target for your schedule. - Update the data date of the current schedule - In the bar chart, hide all the bars but the Target Bar. Hope this helps
Member for
16 years 9 monthsRE: How to Move Date Sight Line?
Thanks everyone.
Member for
18 years 5 monthsRE: How to Move Date Sight Line?
1. Click Data
2. Click Calendars...
3. Click Global Calendar
4. Click Standard...
5. Select a new date under Data Date
Close windows
Now your schedule has new sight line as per your new data date without any change in the schedule.
TAAAADAAAA
Member for
16 years 9 monthsRE: How to Move Date Sight Line?
Not sure why, but when I go to copy the schedule it keeps telling me "Invalid Project Name".
Any ideas?
Member for
18 years 9 monthsRE: How to Move Date Sight Line?
Hi Sam,
If it is only for printing, a turnaround for your problem may be:
(Make backups before !)
- Make a copy of your schedule,
- Set the copy as a target for your schedule.
- Update the data date of the current schedule
- In the bar chart, hide all the bars but the Target Bar.
Hope this helps