How to Move Date Sight Line?

Member for

18 years 5 months

1. Click Data

2. Click Calendars...

3. Click Global Calendar

4. Click Standard...

5. Select a new date under Data Date

Close windows

Now your schedule has new sight line as per your new data date without any change in the schedule.



TAAAADAAAA

Member for

16 years 9 months

Not sure why, but when I go to copy the schedule it keeps telling me "Invalid Project Name".



Any ideas?

Member for

18 years 9 months

Hi Sam,



If it is only for printing, a turnaround for your problem may be:

(Make backups before !)

- Make a copy of your schedule,

- Set the copy as a target for your schedule.

- Update the data date of the current schedule

- In the bar chart, hide all the bars but the Target Bar.



Hope this helps