You cannot do that in P6, you can only drag each activity or group of activites to other level but not at the same level. Because, you assigned sort to all activitvies by Field name & Sort order.
Yes, you can do that in P3 however, it will goes back to its original order or sequence if you will run filter due to the sorting.
anyway if you intend to move it so you can relate it to other activities, you dont need to. relationsihps are created in the order you pick the activities in P6
Member for
18 years 6 monthsRE: Move an Activity Up or Down By P6
Hi Abeer,
You cannot do that in P6, you can only drag each activity or group of activites to other level but not at the same level. Because, you assigned sort to all activitvies by Field name & Sort order.
Yes, you can do that in P3 however, it will goes back to its original order or sequence if you will run filter due to the sorting.
Regards.
Member for
17 yearsRE: Move an Activity Up or Down By P6
Hmmm. so far i dont know how. maybe you cant
anyway if you intend to move it so you can relate it to other activities, you dont need to. relationsihps are created in the order you pick the activities in P6