For hammock activities, You have to update actual start date and actual finish date. The percentage of hammock activities shall be automatically calculated.
To create a Hammock Activity, create a new activity in their specific level and change the activity type to "hammock" then tie up with the predecessor (SS) & successor (FF).
HTH.
Arnold
Member for
16 years 11 months
Member for16 years11 months
Submitted by Ernani Garena on Sat, 2008-12-06 08:04
Hammock is used when in an activity start and end dates are known and we want it (activity) to pick duration and adjust itself within the limits (start and end dates).
You can find hammock activities used in Cranes and Hoists section of our programme.
Member for
17 years 11 monthsRE: Updatingn the schedule in P-3
For hammock activities, You have to update actual start date and actual finish date. The percentage of hammock activities shall be automatically calculated.
Cheers,
Member for
18 years 6 monthsRE: Updatingn the schedule in P-3
Hi Ernani,
To create a Hammock Activity, create a new activity in their specific level and change the activity type to "hammock" then tie up with the predecessor (SS) & successor (FF).
HTH.
Arnold
Member for
16 years 11 monthsRE: Updatingn the schedule in P-3
Hello! Can anybody teach me how to create hammock activities. A sample schedule will be of great help for me to understand more hammock activities.
You can email me thru ernan0518@gmail.com
Thank you very much!
Member for
16 years 11 monthsRE: Updatingn the schedule in P-3
Hammock is used when in an activity start and end dates are known and we want it (activity) to pick duration and adjust itself within the limits (start and end dates).
You can find hammock activities used in Cranes and Hoists section of our programme.
Member for
17 years 1 monthRE: Updatingn the schedule in P-3
Thank you!!
Member for
16 years 11 monthsRE: Updatingn the schedule in P-3
No Ali
You do not have to update a Hammock it is updated automaticly.