Updatingn the schedule in P-3

Member for

17 years 11 months

For hammock activities, You have to update actual start date and actual finish date. The percentage of hammock activities shall be automatically calculated.



Cheers,

Member for

18 years 6 months

Hi Ernani,



To create a Hammock Activity, create a new activity in their specific level and change the activity type to "hammock" then tie up with the predecessor (SS) & successor (FF).



HTH.



Arnold


Member for

16 years 11 months

Hello! Can anybody teach me how to create hammock activities. A sample schedule will be of great help for me to understand more hammock activities.



You can email me thru ernan0518@gmail.com



Thank you very much!

Member for

16 years 11 months

Hammock is used when in an activity start and end dates are known and we want it (activity) to pick duration and adjust itself within the limits (start and end dates).



You can find hammock activities used in Cranes and Hoists section of our programme.

Member for

16 years 11 months

No Ali



You do not have to update a Hammock it is updated automaticly.