Thanks Guys, Ive also tested it now and indeed it seems to work. Data (dates, work) etc get rolled up the two separate hierarchies and also logical links flow freely across both dimensions.
Im going to enjoy exploring this further.
Paul.
Member for
19 years 5 months
Member for19 years5 months
Submitted by Mark Chapman on Wed, 2008-10-29 07:39
Member for
18 years 8 monthsRE: Multiple Master Projects (MSP)
Thanks Guys, Ive also tested it now and indeed it seems to work. Data (dates, work) etc get rolled up the two separate hierarchies and also logical links flow freely across both dimensions.
Im going to enjoy exploring this further.
Paul.
Member for
19 years 5 monthsRE: Multiple Master Projects (MSP)
Ive just tested this and this works. You cannot insert the same project twice but you can have a project inserted to 2 different programmes.
This took about 1 min to test. I hope this helps.
Mark
Member for
22 years 9 monthsRE: Multiple Master Projects (MSP)
Paul,
as far as I know, you cannot insert a same project more than once, i.e. one project cannot be a sub- yto more than one master-
you could use hyperlinks between sub-project taks instead
Alexandre