Primavera Project Planner - P3 Member for 18 years 4 months Member for 18 years 5 months Submitted by Sajid Balma on Sat, 2008-10-18 01:22 Permalink RE: how to unstatus a project in P3 Absolutely, but with a minor change.... There should be a space between the quotes to run this Global Change. Else it keeps giving you Invalid Data error. Regards Member for 24 years 6 months Member for 24 years 7 months Submitted by Paul Harris on Fri, 2008-10-17 08:05 Permalink RE: how to unstatus a project in P3 Richard It goes something like this AS EQ "" AF EQ "" PCT EQ 0 OD EQ RD Paul E Harris Eastwood Harris Pty Ltd, Melbourne, Australia Planning and Scheduling Training Manual & Book Publishers, Consulting and Training www.eh.com.au Log in or register to post comments
Member for 18 years 4 months Member for 18 years 5 months Submitted by Sajid Balma on Sat, 2008-10-18 01:22 Permalink RE: how to unstatus a project in P3 Absolutely, but with a minor change.... There should be a space between the quotes to run this Global Change. Else it keeps giving you Invalid Data error. Regards
Member for 24 years 6 months Member for 24 years 7 months Submitted by Paul Harris on Fri, 2008-10-17 08:05 Permalink RE: how to unstatus a project in P3 Richard It goes something like this AS EQ "" AF EQ "" PCT EQ 0 OD EQ RD Paul E Harris Eastwood Harris Pty Ltd, Melbourne, Australia Planning and Scheduling Training Manual & Book Publishers, Consulting and Training www.eh.com.au
Member for
18 years 4 monthsRE: how to unstatus a project in P3
Absolutely, but with a minor change....
There should be a space between the quotes to run this Global Change. Else it keeps giving you Invalid Data error.
Regards
Member for
24 years 6 monthsRE: how to unstatus a project in P3
Richard
It goes something like this
AS EQ ""
AF EQ ""
PCT EQ 0
OD EQ RD
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
www.eh.com.au