Thats not a bug, you need to go into View>Bars, sounds as though the logic is showing on the baseline, not the current tasks....
Important...In The view bars menu ( list of different types )...the LOWER the order in the menu screen the HIGHER the priority, so youll need to ensure that the current task bars / milestones ( including complete bars / critical bars / milestones are below the baseline bars / milestones..
Thanks this should do it, as soon as I get Metaframe set up in my computer I will work on it.
Today I asked the scheduler for a very simple schedule, 24 activities, for a presentation but for some reason the dependancy arrows show incorrect relationships, do it ever happened to you. Is it a bug or our scheduler?
Member for
16 years 9 monthsRE: Driving Predecessors
David, thank you very much, keep hanging around just in case we need your advise again.
R. Davila
Member for
16 years 9 monthsRE: Driving Predecessors
Hi there,
glad to be of assistance,
Thats not a bug, you need to go into View>Bars, sounds as though the logic is showing on the baseline, not the current tasks....
Important...In The view bars menu ( list of different types )...the LOWER the order in the menu screen the HIGHER the priority, so youll need to ensure that the current task bars / milestones ( including complete bars / critical bars / milestones are below the baseline bars / milestones..
This should sort it !
Regards,
David Garside
Member for
16 years 9 monthsRE: Driving Predecessors
Thanks this should do it, as soon as I get Metaframe set up in my computer I will work on it.
Today I asked the scheduler for a very simple schedule, 24 activities, for a presentation but for some reason the dependancy arrows show incorrect relationships, do it ever happened to you. Is it a bug or our scheduler?
R Davila