Actually, I want to change the calender for the project.
Now, if i go to Enterprise --> Project --> Defaults, then we can chnage the calender there, but it will be effective only for all new activities to be inserted.
How, can I change the calender for the existing activities. (Say, there are 450+ activities).
If I change it from Enterprise - Calender, then it gives the below mentyioned code.
Member for
9 years 9 monthsDeaR aLL, This mesage showing
DeaR aLL,
This mesage showing everytime when print preview and page set up. event code JPEGE-2077-2
Do you have any solution on this. Appreciated help
Member for
18 years 6 monthsRE: Event Code 2DVWV-3590-8
Youre always Welcome Rav..
Member for
18 years 5 monthsRE: Event Code 2DVWV-3590-8
Such a silly thing....
Thanks Arnold for d help.
Member for
18 years 6 monthsRE: Event Code 2DVWV-3590-8
Hi Raviraj,
You can change your calendar for the existing Activities using GLOBAL CHANGE.
Calendar = "Select Assign Calendar"
If you Wanted to change the selected activities only then you need to filter prior to run Global change.
Arnold
Member for
18 years 5 monthsRE: Event Code 2DVWV-3590-8
NO REPLY!!!!!!
Actually, I want to change the calender for the project.
Now, if i go to Enterprise --> Project --> Defaults, then we can chnage the calender there, but it will be effective only for all new activities to be inserted.
How, can I change the calender for the existing activities. (Say, there are 450+ activities).
If I change it from Enterprise - Calender, then it gives the below mentyioned code.
Is there any way out??
Member for
18 years 8 monthsRE: Event Code 2DVWV-3590-8
Hi,
I too get the following message while changing layout
"An application event has been intercepted. Please note the event code for refrence.
Event Code AVAAO-0596-E"
After that P6 closes.
I contacted Primavera, but not heard anything from them.
Cheers.
Richu