SPI & CPI

Member for

17 years 3 months

Thanks to all

Member for

18 years 6 months

Hi,



SCHEDULE PERFORMANCE INDEX (SPI) – the ratio of work performed (earned value or BCWP) to work scheduled (planned value or BCWS).



COST PERFORMANCE INDEX / INDICATOR (CPI) – the ratio of earned value to actual costs (CPI = BCWP/ACWP). A value greater than 1 indicates that costs are running under budget. A value less than 1 indicates that costs are running over budget. Often used to predict magnitude of a possible cost overrun by dividing it into the original cost estimate (original cost estimate / CPI = projected cost at completion).

Member for

17 years 8 months

Hi,

SPI = Schedule performance index

CPI = Cost performance index

Please see details P3 manual or help.



Shaneouz