Primavera Project Planner - P3 Member for 22 years 7 months Member for 22 years 7 months Submitted by Joao Ribeiro on Wed, 2008-07-30 12:54 Permalink RE: Global change Glad to be of help. Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Wed, 2008-07-30 12:48 Permalink RE: Global change Joao, it works, it works! Muchas gracias, hombre Member for 22 years 7 months Member for 22 years 7 months Submitted by Joao Ribeiro on Wed, 2008-07-30 12:39 Permalink RE: Global change Yes, I think the answer is: then RES EQ(AD) XYZ and RDRV EQ "*" Using it to turn all selected resources into driving. Or, perhaps, using two steps: - First, changing the resources - Second ,converting then to driving. It is also advisable to use "Trial Run" first, just in case... Good luck Bonne chance. Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Wed, 2008-07-30 12:09 Permalink RE: Global change Joao, Thanks for answering my post Maybe I was not clear enough Is it posisble to change the "Driving resource" check box in the Activity Details Resource window by using the "Then" section in Global Change e.g. If ACT EQ 1234 then RDRV EQ YES and RES EQ XYZ Thanks for your help, Gracias por ayudar me Member for 22 years 7 months Member for 22 years 7 months Submitted by Joao Ribeiro on Wed, 2008-07-30 12:02 Permalink RE: Global change Use " " or "*" for non resource driving, resource driving with EQ or NE. HTH Log in or register to post comments
Member for 22 years 7 months Member for 22 years 7 months Submitted by Joao Ribeiro on Wed, 2008-07-30 12:54 Permalink RE: Global change Glad to be of help.
Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Wed, 2008-07-30 12:48 Permalink RE: Global change Joao, it works, it works! Muchas gracias, hombre
Member for 22 years 7 months Member for 22 years 7 months Submitted by Joao Ribeiro on Wed, 2008-07-30 12:39 Permalink RE: Global change Yes, I think the answer is: then RES EQ(AD) XYZ and RDRV EQ "*" Using it to turn all selected resources into driving. Or, perhaps, using two steps: - First, changing the resources - Second ,converting then to driving. It is also advisable to use "Trial Run" first, just in case... Good luck Bonne chance.
Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Wed, 2008-07-30 12:09 Permalink RE: Global change Joao, Thanks for answering my post Maybe I was not clear enough Is it posisble to change the "Driving resource" check box in the Activity Details Resource window by using the "Then" section in Global Change e.g. If ACT EQ 1234 then RDRV EQ YES and RES EQ XYZ Thanks for your help, Gracias por ayudar me
Member for 22 years 7 months Member for 22 years 7 months Submitted by Joao Ribeiro on Wed, 2008-07-30 12:02 Permalink RE: Global change Use " " or "*" for non resource driving, resource driving with EQ or NE. HTH
Member for
22 years 7 monthsRE: Global change
Glad to be of help.
Member for
22 years 9 monthsRE: Global change
Joao,
it works, it works!
Muchas gracias, hombre
Member for
22 years 7 monthsRE: Global change
Yes, I think the answer is:
then RES EQ(AD) XYZ
and RDRV EQ "*"
Using it to turn all selected resources into driving. Or, perhaps, using two steps:
- First, changing the resources
- Second ,converting then to driving.
It is also advisable to use "Trial Run" first, just in case...
Good luck
Bonne chance.
Member for
22 years 9 monthsRE: Global change
Joao,
Thanks for answering my post
Maybe I was not clear enough
Is it posisble to change the "Driving resource" check box in the Activity Details Resource window by using the "Then" section in Global Change
e.g.
If ACT EQ 1234
then RDRV EQ YES
and RES EQ XYZ
Thanks for your help,
Gracias por ayudar me
Member for
22 years 7 monthsRE: Global change
Use " " or "*" for non resource driving, resource driving with EQ or NE.
HTH