Non-Contractor Caused Delay

Member for

18 years 10 months

Thank you Kieran, Larry, sathis and Sherif for replying..



I appreciate your contribution ..



I will update you with the way it will be solved ..



Sherif, the contract conditions are not standard conditions like FIDIC or nec3, ... they are specially written to this project ..

Member for

20 years 6 months

Which type of Contract is the project? (FIDCI, nec3,...).



I case of Fidic; please specify which revision.

Member for

18 years

Larry



Your are correct, other than interest rate could not entitle, although he has to prove.

Member for

18 years

Naimran,



In my opinion, I don’t think that Advance Payment (A/P) should be linked from project mobilization cost such as LC in your case.



Basically, the initial cost expenses such as mobilization cost, etc. should come from the project operating cost which is sourced from Contractor’s own account.



In case of Employers late payments of such A/P, Contractor is reasonably entitled to receive an interest rate for the period of delay.



Good day

Member for

21 years 9 months

Good morning Nariman



Sounds like a good question for another long thread. One with many possible answers but at the end of the day it will be down to the terms & conditions set out in the contract between the client (the plaintiff) & the principle contractor (the defence). And not knowing these in detail then see below.



A brief summary;



If it was agreed that orders (or a clause that orders over a certain amount) would not be placed by the principle contractor unless funds were released by the client... you see were this is going, then the principle contractor cannot be at fault.



If no terms were in the contract and the client believed they had chosen a contractor with a big enough wallet to cover costs until costs were invoiced properly disregarding the amount and terms of the sub contractor (probably the smartest client in legal & financial terms), then the principle contractor doesn’t have a leg to stand on.



In summary of above, if the client has drawn up a fairly air tight contract then you is stuffed. Best advice is go and see the leagl team who negotiated the contract with the client and ask them where does the principle contractor stand. They are the best people to see in these circumstances.



Please let PP know how it turns out.



Cheers



Kieran



PS> T&C’s on a pear shaped projects can be cruicial and certainly interesting for future projects.