Primavera Project Planner - P3 Member for 18 years 9 months Member for 18 years 9 months Submitted by Ife Olyke on Thu, 2008-07-24 08:31 Permalink RE: Progress Import & Actual Duration planning unit is in hours and not days... thanks for pointing that out, cos i forgot to mention it earlier... Member for 20 years Member for 20 years 1 month Submitted by Warren Tolentino on Thu, 2008-07-24 03:13 Permalink RE: Progress Import & Actual Duration Bro; Just please check your calendar. You are in days duration that is why when you put your actual start same as finish the duration will of course be 0. Please remember that your activity is a task type, so it needs a duration to show. Member for 18 years 9 months Member for 18 years 9 months Submitted by Ife Olyke on Wed, 2008-07-23 11:53 Permalink RE: Progress Import & Actual Duration I just realised it didnt post properly; Sometimes when I import progress into P3 say in the order below; Activity Id = AB1000 Percentage = 100% Actual Start = 23/07/08 Actual Finish = 23/07/08 P3 stores the Actual start and finish dates in the order below; Actual Start = 23JUL08 00:00A Actual Finish = 22JUL08 23:59A Hence making the actual duration 0; has anyone faced this challenge before? Please share how you dealt with it... Thanks... Log in or register to post comments
Member for 18 years 9 months Member for 18 years 9 months Submitted by Ife Olyke on Thu, 2008-07-24 08:31 Permalink RE: Progress Import & Actual Duration planning unit is in hours and not days... thanks for pointing that out, cos i forgot to mention it earlier...
Member for 20 years Member for 20 years 1 month Submitted by Warren Tolentino on Thu, 2008-07-24 03:13 Permalink RE: Progress Import & Actual Duration Bro; Just please check your calendar. You are in days duration that is why when you put your actual start same as finish the duration will of course be 0. Please remember that your activity is a task type, so it needs a duration to show.
Member for 18 years 9 months Member for 18 years 9 months Submitted by Ife Olyke on Wed, 2008-07-23 11:53 Permalink RE: Progress Import & Actual Duration I just realised it didnt post properly; Sometimes when I import progress into P3 say in the order below; Activity Id = AB1000 Percentage = 100% Actual Start = 23/07/08 Actual Finish = 23/07/08 P3 stores the Actual start and finish dates in the order below; Actual Start = 23JUL08 00:00A Actual Finish = 22JUL08 23:59A Hence making the actual duration 0; has anyone faced this challenge before? Please share how you dealt with it... Thanks...
Member for
18 years 9 monthsRE: Progress Import & Actual Duration
planning unit is in hours and not days... thanks for pointing that out, cos i forgot to mention it earlier...
Member for
20 yearsRE: Progress Import & Actual Duration
Bro;
Just please check your calendar. You are in days duration that is why when you put your actual start same as finish the duration will of course be 0. Please remember that your activity is a task type, so it needs a duration to show.
Member for
18 years 9 monthsRE: Progress Import & Actual Duration
I just realised it didnt post properly;
Sometimes when I import progress into P3 say in the order below;
Activity Id = AB1000
Percentage = 100%
Actual Start = 23/07/08
Actual Finish = 23/07/08
P3 stores the Actual start and finish dates in the order below;
Actual Start = 23JUL08 00:00A
Actual Finish = 22JUL08 23:59A
Hence making the actual duration 0; has anyone faced this challenge before? Please share how you dealt with it... Thanks...