There is no risk to the integrity of data using the P3 import function as long as your data is correct. There is a technical article on my web site that explains how to import through Excel, but always back up you file before commencing.



To delete all the relationships in a P3 project I usually delete the ***REL.P3 and replace it with a file from a project that has no relationships and rename as required.



Paul E Harris