Primavera Project Planner - P3 Member for 17 years 6 months Member for 17 years 6 months Submitted by James Braghini on Fri, 2008-07-11 13:15 Permalink RE: Constarints in Primavera I would not use any contraint on the finish milestone. I would have the drop dead completion date placed in the Project Data. Good luck on you project. James B. Log in or register to post comments
Member for 17 years 6 months Member for 17 years 6 months Submitted by James Braghini on Fri, 2008-07-11 13:15 Permalink RE: Constarints in Primavera I would not use any contraint on the finish milestone. I would have the drop dead completion date placed in the Project Data. Good luck on you project. James B.
Member for
17 years 6 monthsRE: Constarints in Primavera
I would not use any contraint on the finish milestone. I would have the drop dead completion date placed in the Project Data.
Good luck on you project.
James B.