track a project

Member for

17 years 9 months

Faisal,



Here’s what I would suggest...



Reschedule tasks that haven’t started



Tasks should be automatically rescheduled if the precedence logic is correct, if it isn’t try using lag times or reviewing the logic



Let MS Project calculate the % Complete



View > Table > Tracking

By entering actual start, duration / work and remaining duration / work MS Project will calculate the % Complete(s)



How do i know whether my project is on schedule or not



Use the status date and progress line as an aide and check against baseline.



Hope this helps.



Regards,



Darren

Member for

17 years 4 months

i want to know three things



1)Reschedule tasks that haven’t started

2)Let MS Project calculate the % Complete(s)

3) how do i know whether my project is on schedule or not

Member for

17 years 9 months

Hi Faisal,



That’s a bit of a tricky question, you can use MS Project in many ways to track progress.



I’ll try and give you the 5 cent tour and then hopefully you can refine your question a little more.



1) Baseline the project (effort and duration)

2) Track actual start dates and actual effort / duration and remaining effort / duration

3) Reschedule tasks that haven’t started

4) Let MS Project calculate the % Complete(s)



Regards,



Darren