Primavera Project Planner - P3 Member for 19 years 1 month Member for 19 years 1 month Submitted by Anoon Iimos on Fri, 2008-06-13 07:45 Permalink RE: Budgeted cost does not match with generated cash flow im talking of "weighting factor", if you had used "costs" you must update your program with costs, and not with any other options. Member for 17 years 4 months Member for 17 years 5 months Submitted by Albert Balogo on Thu, 2008-06-12 15:26 Permalink RE: Budgeted cost does not match with generated cash flow Yes Anoon, there is three ways on how to update the program duration,resources and cost. these three i used cost. even my friend hes a planner too, he cant resolve this problem. you can try it to your program, just let me know if something remedy. thanks Member for 19 years 1 month Member for 19 years 1 month Submitted by Anoon Iimos on Thu, 2008-06-12 06:45 Permalink RE: Budgeted cost does not match with generated cash flow have you chosen "costs" as your weighting factor before running your schedule? how do you update your schedule? Log in or register to post comments
Member for 19 years 1 month Member for 19 years 1 month Submitted by Anoon Iimos on Fri, 2008-06-13 07:45 Permalink RE: Budgeted cost does not match with generated cash flow im talking of "weighting factor", if you had used "costs" you must update your program with costs, and not with any other options.
Member for 17 years 4 months Member for 17 years 5 months Submitted by Albert Balogo on Thu, 2008-06-12 15:26 Permalink RE: Budgeted cost does not match with generated cash flow Yes Anoon, there is three ways on how to update the program duration,resources and cost. these three i used cost. even my friend hes a planner too, he cant resolve this problem. you can try it to your program, just let me know if something remedy. thanks
Member for 19 years 1 month Member for 19 years 1 month Submitted by Anoon Iimos on Thu, 2008-06-12 06:45 Permalink RE: Budgeted cost does not match with generated cash flow have you chosen "costs" as your weighting factor before running your schedule? how do you update your schedule?
Member for
19 years 1 monthRE: Budgeted cost does not match with generated cash flow
im talking of "weighting factor", if you had used "costs" you must update your program with costs, and not with any other options.
Member for
17 years 4 monthsRE: Budgeted cost does not match with generated cash flow
Yes Anoon, there is three ways on how to update the program duration,resources and cost. these three i used cost. even my friend hes a planner too, he cant resolve this problem. you can try it to your program, just let me know if something remedy.
thanks
Member for
19 years 1 monthRE: Budgeted cost does not match with generated cash flow
have you chosen "costs" as your weighting factor before running your schedule? how do you update your schedule?