Microsoft Project Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Thu, 2008-05-29 14:24 Permalink RE: Problem with resource pool Hi Chris, are you using MS Project Std, or Pro + Server? I guess its Std? Are you sure you have saved the file #4 after resources were assigned to tasks? Have you tried linking another project file to the same resource pool and using resources? if it works, that means that your current file #4 is corrupted Alexandre Log in or register to post comments
Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Thu, 2008-05-29 14:24 Permalink RE: Problem with resource pool Hi Chris, are you using MS Project Std, or Pro + Server? I guess its Std? Are you sure you have saved the file #4 after resources were assigned to tasks? Have you tried linking another project file to the same resource pool and using resources? if it works, that means that your current file #4 is corrupted Alexandre
Member for
22 years 9 monthsRE: Problem with resource pool
Hi Chris,
are you using MS Project Std, or Pro + Server?
I guess its Std?
Are you sure you have saved the file #4 after resources were assigned to tasks?
Have you tried linking another project file to the same resource pool and using resources? if it works, that means that your current file #4 is corrupted
Alexandre