Critical Path in P3 w/o Longest Path

Member for

18 years 1 month

you can fix a number for the total float and the filter will display all activities having a TF less than this number...



Total float LT (x)

Member for

22 years 10 months

You seem to infer that all activities listed as being on the critical path must have the same float in order to be a valid critical path. This was never a part of the definition of “critical path.”



Many issues can cause the longest chain of activities to have different float; activity and resource calendars, interruptible activities, start versus finish float, and constraints come to mind immediately. For more on this, I suggest that you review a paper that I once presented titled, “Longest Path Value” on my website at http://ronwinterconsulting.com/published.htm. Good luck!