Primavera Project Planner - P3 Member for 22 years 8 months Member for 22 years 9 months Submitted by Alex Wong on Sun, 2008-05-25 21:18 Permalink RE: Linking Projects Jineesh Assume u are using P3 3.1 - Since your posting is in this forum categories. All you need to do is to have a master project and 4 sub-projects and with a filter to filter our the critical milestone. The sub-project can be updated independent to the master program. HTH Alex Log in or register to post comments
Member for 22 years 8 months Member for 22 years 9 months Submitted by Alex Wong on Sun, 2008-05-25 21:18 Permalink RE: Linking Projects Jineesh Assume u are using P3 3.1 - Since your posting is in this forum categories. All you need to do is to have a master project and 4 sub-projects and with a filter to filter our the critical milestone. The sub-project can be updated independent to the master program. HTH Alex
Member for
22 years 8 monthsRE: Linking Projects
Jineesh
Assume u are using P3 3.1 - Since your posting is in this forum categories.
All you need to do is to have a master project and 4 sub-projects and with a filter to filter our the critical milestone.
The sub-project can be updated independent to the master program.
HTH
Alex