One Day Activity - when does it end?

Member for

19 years 11 months

"Default Start time: 09:00

Default end time: 17:00"



Here, I think, is your problem.

Check the Project Calendar (Project, Project Information), which I bet is using the Standard Calendar and, if i can assume it is unchanged from the original, the day starts at 0800, there is a 1 hour break and and end of day at 1700, for 8 hours per day.

So, although your calendar for the project, task and resource allows for a start time of 0800, every time you create a task it starts at 0900 according to Tools, Options as above.

Member for

17 years 9 months

Hi Bijaya,



As well as the excellent suggestions from Bertrand, Alexandre and Trevor, I would include another option. If the duration for the task is not a whole day (1.13 days instead of 1 day).



What you also need to bear in mind is, if any of the suggestions has happened previously in the schedule and the task you are trying to get to finish on the same day has them as a predecessor in some way, shape or form, then that naturally will affect your problem task.



I also recommend you alter the date format (Tools > Options > View) so that it includes time (Wed 21/05/08 08:00). It will enable you to spot any deviation in the Start / Finish times, once you have finished checking the Start / Finish times you can always change it back to you default view.



MS Project only cares about hours per day and 1 day duration is 8hrs NOT 24hrs. As an example Task B cannot start until Task A has finished:



Task A has a duration of 5.13 days

Task B has a duration of 1 days



If you have time showing in the Start / Finish fields you can immediately see the problem...



Task A starts Wed 14/05/08 08:00 and finishes Wed 21/05/08 09:02

Task B starts Wed 21/05/08 09:02 and finishes Thu 22/05/08 09:02



You would expect the finish time for Task B to be Wed 21/05/08 18:02, but the default finish time is set at 17:00. In this instance MS Project uses 62 mins from the next day to make up the 8hr total (the time from 17:00 to 08:00 is dead time and not used in duration calculation unless you use edays or 24hr calendar), it then has a knock-on effect on the task successors.



If you don’t show the time in your Start / Finish fields you will only see Task B starting Wed 21/05/08 and finishing Thu 22/05/08.



Regards,



Darren

Member for

20 years 8 months

Trevor,



Tool, Option,Schedule shows

Show scheduling message (unticked)

Show assignment units as a: Decimal

New tasks: Start On Project Start Date

Durations is entered in: Days

Work in entered in: Hours

Default task type: Fiaxed Units

New taks are efforct drive (Ticked)

Autolink inserted on moved tasks (Ticked)

Split in progress tasks (Ticked)

Tasks will always honor their constraint dates (Ticked)

Show that tasks have estimated durations (Ticked)

New Tasks have estimated durations (Ticked)





Similarly Tools, Options, Calendar shows



Calendar options for ’Project2’

Week starts on: Monday

Fiscal Year starts in: January

Default Start time: 09:00

Default end time: 17:00



Hours per day 8:00

Hours per week: 40:00

Days per month: 20



They are all default settingss and I do not want to bother with start time and finish time in the schedule. Days are perfectly fine.

Member for

19 years 11 months

I tried it and the task starts at 08:00 and finishes at 17:00 on 20/05/2008.



You need to check:

Tools,Options, Schedule.

Tools,Options, Calendar.

Also check the Project Calendar and any Task and/or Resource Calendars in use.

Member for

22 years 9 months

Bijaya,

at what time does your 1 day activity finish on May 21st?

you should check the following:

1. Tools, Options, Calendar: Default start time

2. Tools, Change working time: does May 20th starts at the same time as 1), sooner, later?

3. Project, Project information: Project start time: same question as 2

Display the date and time to be able to check these 3 points, and hide the time when you are finished

Hope this will help you,

Alexandre

Member for

20 years 8 months

Try it yourself. You will still get 21 May as Finish Date.



I do not want to show time in my date column - most would not want it.


Member for

18 years 8 months

Hi,



Don’t you use elapsed days ?



exemple:

Task1 D:1 days S:20/05/08 08:00 F:20/05/08 17:00

Task2 D:1 edays S:20/05/08 08:00 F:21/05/08 08:00