Primavera Project Planner - P3 Member for 19 years 1 month Member for 19 years 1 month Submitted by Anoon Iimos on Sat, 2008-05-17 06:18 Permalink RE: Fixing the Late Finish Date in P3 it is because you have negative floats and constraints and the activity-progress is going out of sequence, you have options for scheduling, retained logic and progress override - you can play with it Log in or register to post comments
Member for 19 years 1 month Member for 19 years 1 month Submitted by Anoon Iimos on Sat, 2008-05-17 06:18 Permalink RE: Fixing the Late Finish Date in P3 it is because you have negative floats and constraints and the activity-progress is going out of sequence, you have options for scheduling, retained logic and progress override - you can play with it
Member for
19 years 1 monthRE: Fixing the Late Finish Date in P3
it is because you have negative floats and constraints and the activity-progress is going out of sequence, you have options for scheduling, retained logic and progress override - you can play with it