The hammock is just considering the first with the s-s relat. and the end with f-f relationship, in a chain.
If any activity in the middle of the chian is going out of the originally first and last teh hammock is not covering it any more. Or You have to chekc every update time.
With Wbs just put it and define the level must summarize.
Much more easier. If your purpose is just summarize a group of activities.
Member for
21 years 3 monthsRE: hammok activity update
Attached is the write-up by myself regarding Hammock Activities. Please review for your reference.
Go to the
http://www.htcprojectcontrols.com/TTB2004-6.pdf
Eric Chou, PE
HTC Project Controls, Inc.
Member for
22 years 3 monthsRE: hammok activity update
Why You do not use Wbs activities?
The hammock is just considering the first with the s-s relat. and the end with f-f relationship, in a chain.
If any activity in the middle of the chian is going out of the originally first and last teh hammock is not covering it any more. Or You have to chekc every update time.
With Wbs just put it and define the level must summarize.
Much more easier. If your purpose is just summarize a group of activities.
Member for
21 years 5 monthsRE: hammok activity update
since hammocks are attached to the earliest start date and the latest finsh dates, any updates will automatically will be incorporated
Member for
22 years 3 monthsRE: hammok activity update
Hammock should be update automatically by P3.
As per instruction given in the manual for summarizing activities.
You should not need to update them, as well as the wbs activities.
Member for
23 years 8 monthsRE: hammok activity update
Which field you are updating in Hammock?