Retainage in P3

Member for

20 years 5 months

Dont show the cost complete 100%. Make the cost% idependent to progress duration% in auto cost rule of P3.

you can even show the activity as completed but cost part you can claim later when you want.

Member for

21 years 6 months

what you could do is taking off a percentage of the cost on each activity and put the remainder on a milestone until the terms are in accordance with the terms of the construction contract.



Once everything is correct with the contract, you can "release" the milestone and mark it 100%.



withholding a certain percentage of progress on the activities will cause out-of-sequence progressing and might "mess up" your schedule.