what you could do is taking off a percentage of the cost on each activity and put the remainder on a milestone until the terms are in accordance with the terms of the construction contract.
Once everything is correct with the contract, you can "release" the milestone and mark it 100%.
withholding a certain percentage of progress on the activities will cause out-of-sequence progressing and might "mess up" your schedule.
Member for
20 years 5 monthsRE: Retainage in P3
Dont show the cost complete 100%. Make the cost% idependent to progress duration% in auto cost rule of P3.
you can even show the activity as completed but cost part you can claim later when you want.
Member for
21 years 6 monthsRE: Retainage in P3
what you could do is taking off a percentage of the cost on each activity and put the remainder on a milestone until the terms are in accordance with the terms of the construction contract.
Once everything is correct with the contract, you can "release" the milestone and mark it 100%.
withholding a certain percentage of progress on the activities will cause out-of-sequence progressing and might "mess up" your schedule.