Task duration less than elapsed time??

Member for

17 years 6 months

Hi Darren,



Thanks for the reply, sorry I’m confusing things and I don’t even know how, I’ve just gone back to check what I’ve done and yep, following your guide gives the right result!!



I was trying to show the same without Task 3 - ie is there any way to show in MSP a floating task whos start date is driven by Task 1 but whos end date is driven by elapsed time (a date) rather than task duration i.e avoiding the need to add Task 3 as a successor. ie the delivery window is say 80days but the delivery process is 60days.



Thanks




Member for

17 years 9 months

Hi Sara,



It seems a little strange that the end milestone date would move the start date of Task 1, if everything is linked correctly.



I’m assuming that you have already set the project start date and that the activities are being driven by precedence rather that constraints.



I’m also assuming that the schedule looks something like this



Task 1 Duration 1d and has a FS relationship with Task 2

Task 2 Duration 60d and has a FS relationship with Task3

Task 3 Duration 0d and has a FNET constraint 04/08/08



Task 1 Starts 15/04/08 Finishes 15/04/08

Task 2 Starts 16/04/08 Finishes 10/07/08 (Inc. Bank Holidays)

Task 3 Starts 04/08/08 Finishes 04/08/08



Another question is, do you have the ’Tasks will always honor their constraint dates’ checkbox ticked? (Tools > Options > Schedule Tab)



Regards,



Darren