Recommend that you check both activity and duration type sand refer to the user manual. Resource dependant tasks can chenge durations if actuals are applied. Durations can change if resources are altered.
Member for
23 years 11 months
Member for23 years11 months
Submitted by David Forrest on Wed, 2004-05-05 05:46
Recommend that you check both activity and duration type sand refer to the user manual. Resource dependant tasks can chenge durations if actuals are applied. Durations can change if resources are altered.
Ok Then just check bars format, and make sure about what kind of summary bar youve selected ( current bar summary, first baseline summary, 2nd baseline summary, remaining bar summary..etc.) all the best!
Thanks for ur reply. I have Primary Baseline for my current update. BL Start & BL Finish dates are not changing. Only the original duration in the current project summary bar is changing.
Regards
Afzal
Member for
21 years 9 months
Member for21 years10 months
Submitted by Hadi k. Shabibi on Tue, 2004-04-13 08:19
Member for
23 years 11 monthsRE: P3e Ver 3.5.1 Original Duraiton changing while
Recommend that you check both activity and duration type sand refer to the user manual. Resource dependant tasks can chenge durations if actuals are applied. Durations can change if resources are altered.
Member for
23 years 11 monthsRE: P3e Ver 3.5.1 Original Duraiton changing while
Recommend that you check both activity and duration type sand refer to the user manual. Resource dependant tasks can chenge durations if actuals are applied. Durations can change if resources are altered.
Member for
16 years 9 monthsRE: P3e Ver 3.5.1 Original Duraiton changing while
Hi,
Ok Then just check bars format, and make sure about what kind of summary bar youve selected ( current bar summary, first baseline summary, 2nd baseline summary, remaining bar summary..etc.) all the best!
Bye
hadi
Member for
21 years 7 monthsRE: P3e Ver 3.5.1 Original Duraiton changing while
Hi,
Thanks for ur reply. I have Primary Baseline for my current update. BL Start & BL Finish dates are not changing. Only the original duration in the current project summary bar is changing.
Regards
Afzal
Member for
21 years 9 monthsRE: P3e Ver 3.5.1 Original Duraiton changing while
Hi!
Did you select primary or secondary baseline ?
Did the BL Start & BL Finish changed as well for the activities
Please check that !!I think you need to creat a baseline
and use one of three methods for updating .
Bye