Primavera Project Planner - P3 Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Thu, 2008-03-27 05:12 Permalink RE: RESOURCE PLANNING Shrikant, a) create resources in Data, Resources b) open the activity form at the bottom of the scree, then click the RES button to open the Resource sub-form c) select the 1st activity to which assign a ressource d) click in the 1st avaliable column in the RES sub-form, select the resource from the drop-down list, enter either Budgeted Quantity or Units per Day .... Regards, Alexandre Log in or register to post comments
Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Thu, 2008-03-27 05:12 Permalink RE: RESOURCE PLANNING Shrikant, a) create resources in Data, Resources b) open the activity form at the bottom of the scree, then click the RES button to open the Resource sub-form c) select the 1st activity to which assign a ressource d) click in the 1st avaliable column in the RES sub-form, select the resource from the drop-down list, enter either Budgeted Quantity or Units per Day .... Regards, Alexandre
Member for
22 years 9 monthsRE: RESOURCE PLANNING
Shrikant,
a) create resources in Data, Resources
b) open the activity form at the bottom of the scree, then click the RES button to open the Resource sub-form
c) select the 1st activity to which assign a ressource
d) click in the 1st avaliable column in the RES sub-form, select the resource from the drop-down list, enter either Budgeted Quantity or Units per Day
....
Regards,
Alexandre