REDUCED MANHOURS DURING RAMADAN

Member for

22 years 9 months

Kier,

assuming that your project’s planning unit is Day:

a) create a new calendar in which you will have one working day less than the regular calendar (i.e. Sat - Tue instead of Sat - Wen if your regular week is 5 days from Saturday)

b) assign this new calendar to activities that will occur during the month of ramadhan

I have used this procedure to schedule projects in Algeria, result is that an 5 day activity will span from saturday morning to next saturday evening

All the best,

Alexandre