Thanks guys- done and working, must have been a glitsch somewhere as I made a new copy of the project and it worked.

Member for

18 years 5 months

Hi Jamie,



Go to Tools --> Graphic report --> Resource & Cost



Go to CONTENT tab and tick the TARGET1 box



U must have set target before doing this.



Select the resource / cost item, whatvere u want and say RUN.



It shud work for u



Cheers,



Ravi

Member for

21 years 1 month

Hi Jamie,



Try exporting the data out of P3 via an Excel spreadsheet format, first for Target then for the current plan.



Then combine your data and produce your Target / Current chart on a user friendly graph.



Regards



John L.

Member for

19 years 1 month

no problem, if you want more, do not hesitate to hire me

Member for

18 years 6 months

Thanks Anoon all done as you suggested and no luck....

Member for

19 years 1 month

make sure your Target Plan is resource loaded; update it that it has progressed perfectly as planned; and make your histogram