There is one more article on Rons website for BASELINE SCHEDULE ANALYSIS. This article I am using from so many years and it will give you an in-depth idea of how to analyse the baseline program.
Thanks Ron, I am now moving in the right direction. Been ussing F9 too long, I guess.
Looked at your Schedule Analyzer. Looks like a great tool, just a little too rich for my blood and I would probably need both versions. I assume the P3 version would work with SureTrak?
Again, thanks. Now the other responses make sense.
Member for
22 years 10 months
Member for22 years10 months
Submitted by Ronald Winter on Tue, 2008-01-29 12:34
You must be referring to the report produced when you re-schedule the calculation of the CPM. Go to Tools / Schedule / check all of the checkboxes under Scheduling Report / and then Schedule Now and you should have it. The report is pathetic though. That is one of the reasons why I invented Schedule Analyzer. Good luck!
Member for
18 years 6 months
Member for18 years6 months
Submitted by Dennis Hanks on Tue, 2008-01-29 12:10
I must not have been clear. The report I am looking for will list all activities that do not have either a successor or predessor, any constraints, violated logic, negative float, etc.
I am almost certain I have seen this report before, but it has been awhile. I would prefer that this be in SureTrack 3.0c, but P3.1 will be OK. Again, any thoughts appreciated. Thanks.
Member for
22 years 10 months
Member for22 years10 months
Submitted by Ronald Winter on Tue, 2008-01-29 10:31
I am not sure how running any report will help you check the project integrity. Instead, may I propose that you run the “File Fix” utility program that comes with P3.
Using either Windows Explorer, MyComputer, or just the Start/Run, go to C:\P3WIN\P3PROGS\PFXW.EXE and run this program. Select your desired schedule, check all of the checkboxes and Start. Check the log file produced for any comments. The Help Button will tell you more about the workings. Good luck!
Member for
18 years 5 monthsRE: Check Project Integrity
HI Dennis,
There is one more article on Rons website for BASELINE SCHEDULE ANALYSIS. This article I am using from so many years and it will give you an in-depth idea of how to analyse the baseline program.
http://www.ronwinterconsulting.com/rabaseline.htm
This article is superb!!
Cheers,
Ravi
Member for
18 years 6 monthsRE: Check Project Integrity
Thanks Ron, I am now moving in the right direction. Been ussing F9 too long, I guess.
Looked at your Schedule Analyzer. Looks like a great tool, just a little too rich for my blood and I would probably need both versions. I assume the P3 version would work with SureTrak?
Again, thanks. Now the other responses make sense.
Member for
22 years 10 monthsRE: Check Project Integrity
You must be referring to the report produced when you re-schedule the calculation of the CPM. Go to Tools / Schedule / check all of the checkboxes under Scheduling Report / and then Schedule Now and you should have it. The report is pathetic though. That is one of the reasons why I invented Schedule Analyzer. Good luck!
Member for
18 years 6 monthsRE: Check Project Integrity
I must not have been clear. The report I am looking for will list all activities that do not have either a successor or predessor, any constraints, violated logic, negative float, etc.
I am almost certain I have seen this report before, but it has been awhile. I would prefer that this be in SureTrack 3.0c, but P3.1 will be OK. Again, any thoughts appreciated. Thanks.
Member for
22 years 10 monthsRE: Check Project Integrity
I am not sure how running any report will help you check the project integrity. Instead, may I propose that you run the “File Fix” utility program that comes with P3.
Using either Windows Explorer, MyComputer, or just the Start/Run, go to C:\P3WIN\P3PROGS\PFXW.EXE and run this program. Select your desired schedule, check all of the checkboxes and Start. Check the log file produced for any comments. The Help Button will tell you more about the workings. Good luck!
Member for
18 years 5 monthsRE: Check Project Integrity
Hi Dennis / Mangesh,
Run report series A & B are standard in any P3 program. You can create your own run series.
Go to Tools --> Tabular Reports --> Production
It will show you the list of items for which you want to check the integrity.
Select the item; give it a label say E, G or any letter and then click on MODIFY to suit your needs.
Then go to Schedule and then select the required Run report series.
Hope this will help you better.
Cheers,
Ravi
Member for
18 years 6 monthsRE: Check Project Integrity
Hi
All u can check the project integrity,
go to---> schedule----> click Run Report series A,
U will get all the details u want.
Cheers
Mangesh
Member for
19 years 1 monthRE: Check Project Integrity
P6 has, but how it works?...i dont know