Global update to an old program???

Member for

17 years 10 months

Hi Steve



I am sorry, there is an error in my previous post.

Instead of Early start it should read as Actual start=" "





regards





sam










Member for

17 years 10 months

if the old program has been run previously you may have to run filter to see constraint dates and remove them and then run Global change to effect the following :

change percent complete(pct)to 0(zero), Remaining duration(RD) equal to Original Duration(OD) RD=OD and Early start ES as " " .

Now schedule with new project start date.



hope this would of help.





regards



sam

Member for

18 years 1 month

Hi,

I did not understand exactly your question...What do you mean by updating an old Program? to be used for a future project? when you do update you’ll get Actual Start, Actual Finish and percent complete...No more ES,EF,LS & LF...Global update? Do you mean ’Update Progress’?

If you want to use the ’old’ program as plan for a future project you can change the Start project date in the project Overview menu and schedule ’F9’ the program, than you’ll get your ES, EF, LS & LF with new planned dates starting from the new project start date...





Concerning the update P3 offers several ways of updating your schedule. You can update progress for all activities and resources as a whole; update activities and resources individually; or use a combination of the two methods.



If your project is progressing exactly as planned or if you only need to estimate progress, simply specify the data date or "as-of" date, then have P3 determine which activities have progressed and how much and calculate the remaining durations of activities that have started. P3 also notes which activities have completed and sets their remaining durations to zero.

If your project is not progressing as planned—many activities are out-of-sequence, activities are taking more or less time to complete than originally planned, or actual resource use is exceeding planned use—update activities and

resources individually. This will help you forecast the effects of this unforeseen progress or lack of progress, so that you can take appropriate corrective action wherever necessary.



Most projects progress somewhere between these two situations: some activities are progressing as planned and

some are not. If this is the case, you’ll want to combine the two updating methods. Let P3 calculate your project as if it is progressing exactly as planned, and then individually update those activities and resources that have deviated from the plan.



Regards

JK

Member for

18 years 9 months

Hi Steve

ES,EF,LS, and LF are calculated based on a project’s network logic. If there are no acuals, you’ll simply modify the project’s start date and start Tools --> Schedule --> with report. Constraints may harm the calculation. Read the report!

If there are actuals you’ll have to remove them first, by Global Change.

Regards

Dieter