Primavera Project Planner - P3 Member for 18 years 9 months Member for 18 years 9 months Submitted by Pranab Kumar Deb on Tue, 2007-11-13 07:32 Permalink RE: Split bars Hello Moutaz, I believe you can achieve your requirement with WBS , the WBS will be the main Activity and the lower level will be the constituent sub activities which will make up the WBS. regards Deb Member for 24 years 6 months Member for 24 years 7 months Submitted by Paul Harris on Tue, 2007-11-13 04:23 Permalink RE: Split bars Create many activities, P3 does not have a split function like MSP. Paul E Harris Eastwood Harris Pty Ltd, Melbourne, Australia Planning and Scheduling Training Manual & Book Publishers & Consulting www.eh.com.au Log in or register to post comments
Member for 18 years 9 months Member for 18 years 9 months Submitted by Pranab Kumar Deb on Tue, 2007-11-13 07:32 Permalink RE: Split bars Hello Moutaz, I believe you can achieve your requirement with WBS , the WBS will be the main Activity and the lower level will be the constituent sub activities which will make up the WBS. regards Deb
Member for 24 years 6 months Member for 24 years 7 months Submitted by Paul Harris on Tue, 2007-11-13 04:23 Permalink RE: Split bars Create many activities, P3 does not have a split function like MSP. Paul E Harris Eastwood Harris Pty Ltd, Melbourne, Australia Planning and Scheduling Training Manual & Book Publishers & Consulting www.eh.com.au
Member for
18 years 9 monthsRE: Split bars
Hello Moutaz,
I believe you can achieve your requirement with WBS , the WBS will be the main Activity and the lower level will be the constituent sub activities which will make up the WBS.
regards
Deb
Member for
24 years 6 monthsRE: Split bars
Create many activities, P3 does not have a split function like MSP.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting
www.eh.com.au