but while doing global change consider including criteria for those milestone activities which may not have start dates(say finish milestones) or vice versa as u may require.
Conclusion : you can access few target parameters thru global change options.
cheers to all.
planning planet is really a dynamic forum.
Member for
18 years 1 month
Member for18 years1 month
Submitted by Johny Kesserwany on Tue, 2007-10-30 10:50
I tried making a custom data item with "type start date" in the target project and ran a global change to make all activities with percent complete GT 0 to have this CDI to become Actual start date, but i cant access CDI from main project.
Member for
18 years 1 month
Member for18 years1 month
Submitted by Johny Kesserwany on Tue, 2007-10-30 08:38
Member for
18 years 9 monthsRE: Comparing an update with auto updated target ( p3 3.1)
Yep that does it.
but while doing global change consider including criteria for those milestone activities which may not have start dates(say finish milestones) or vice versa as u may require.
Conclusion : you can access few target parameters thru global change options.
cheers to all.
planning planet is really a dynamic forum.
Member for
18 years 1 monthRE: Comparing an update with auto updated target ( p3 3.1)
In the custom data :
1) create an item name TASD , type S, length:7, Target actual start.
2) do a global change to store all Target actual start dates to TASD
3) Run a filter on TASD
You can repeat these steps to any date in the target.
Regards
Member for
18 years 9 monthsRE: Comparing an update with auto updated target ( p3 3.1)
Dear Johny
Could you further explain this.
I tried making a custom data item with "type start date" in the target project and ran a global change to make all activities with percent complete GT 0 to have this CDI to become Actual start date, but i cant access CDI from main project.
Member for
18 years 1 monthRE: Comparing an update with auto updated target ( p3 3.1)
You can do it by:
1) creating custom data items corresponding to your Early and/or Actual dates in the Target project.
2) run filters on these Custom data items in the current project
Regards
JK
Member for
18 years 9 monthsRE: Comparing an update with auto updated target ( p3 3.1)
Dear Ashraf
but this sometimes may not serve the purpose when we want to show all started activities in updated program along with the target.
usually some activities in updated program starts earlier than planned.
Member for
18 years 6 monthsRE: Comparing an update with auto updated target ( p3 3.1)
Hi,
You can do it otherway around i.e. make (1) the target of (2) and open all started activities of (2) by giving a filter %Comp >0.
Hope this helps ad the resultant filter will be the same as you require.
Regards,
Ashraf