Load your resources in Resource Dictionary , then allocate it in your selected activity.
In your second query, about the earn value. this concept is base on performance index of your work , for me this earn value analysis is the best way to track progress wherein you are using the common denominator of all units.
ULY
Member for
20 years 2 months
Member for20 years2 months
Submitted by ulysses garcia on Fri, 2007-10-26 12:32
Load your resources in Resource Dictionary , then allocate it in your selected activity.
In your second query, about the earn value. this concept is base on performance index of your work , for me this earn value analysis is the best way to track progress wherein you are using the common denominator of all units.
ULY
Member for
18 years
Member for18 years1 month
Submitted by Divya Bhardwaj on Fri, 2007-10-26 08:11
Actually i wanted to know as in when i have allocated manhours/resources to all the activities, how can i know about the earned values/consumption rates
Member for
18 years 7 months
Member for18 years7 months
Submitted by Adedeji Adelaja on Fri, 2007-10-12 03:29
Member for
18 yearsRE: Resource Allocation
hei
Thanks a ton!!!
Can u tell me the Primavers ftp site please
Member for
18 years 5 monthsRE: Resource Allocation
Divya,
Primavera manual is available with the Installation CD or u can get it download from primavera ftp site.
Paul harris book can be ordered from his own web-site www.eh.com.au or is available on www.amazon.com
or you can send private message to Paul Harris for his book.
Cheers,
Ravi
Member for
18 yearsRE: Resource Allocation
Hi
Thanks but where can i get this book from?
Please help, i am in dire need of some good help.
Member for
18 yearsRE: Resource Allocation
Go to Help in Primavera and look for resources and earned value...maybe this will help
Member for
24 years 9 monthsRE: Resource Allocation
Divya
Suggest you get onto Paul Harris and buy one of his excellent books on P3
TITLE Planning Using Primavera Project Planner© P3© Version 3.1
Revised 2006
DATE OF PUBLICATION 30 -Nov-06
NAME OF AUTHOR Paul E Harris
ISBN 978-1-921059-13-1
BINDING A4
www.eh.com.au
Member for
20 years 2 monthsRE: Resource Allocation
Divya,
Load your resources in Resource Dictionary , then allocate it in your selected activity.
In your second query, about the earn value. this concept is base on performance index of your work , for me this earn value analysis is the best way to track progress wherein you are using the common denominator of all units.
ULY
Member for
20 years 2 monthsRE: Resource Allocation
Divya,
Load your resources in Resource Dictionary , then allocate it in your selected activity.
In your second query, about the earn value. this concept is base on performance index of your work , for me this earn value analysis is the best way to track progress wherein you are using the common denominator of all units.
ULY
Member for
18 yearsRE: Resource Allocation
Hi
Actually i wanted to know as in when i have allocated manhours/resources to all the activities, how can i know about the earned values/consumption rates
Member for
18 years 7 monthsRE: Resource Allocation
Please be definite as to your needs