Longest Path, literally means the same as it describes - the longest path from the Start of the Project to Finish of the Project. It DOES include completed activities.
Critical activities can be defined the way you want - it can be activities with less than certain amount of Total Float or it can be the longest path.
Which activities appear in critical path depends on how you set up your critical path filter. Again the filter can be either to select the activities in the longest path or to select activities with TF less than certain amount. If you select Longest path, then your filter will show the LONGEST PATH including completed activities.
The solution is remove the actual finish date from the field, make sure the % of completion is not equal to 100 and remaining duration is not equal to 0.
Any of the above 3 will cause the problem but they are input incorrectly only
Member for
18 years
Member for18 years
Submitted by gilbert gata on Mon, 2007-10-15 18:25
You apparently have the critical path defined as, "the longest path." If an activity on the longest path was completed out-of-sequence (before logically preceding work was complete,) then this completed activity remains on the longest path in order to show the continuity of the path.
Hope that this helps. Good luck!
Member for
18 years 9 months
Member for18 years9 months
Submitted by Pranab Kumar Deb on Wed, 2007-09-19 09:27
Member for
20 years 8 monthsRE: Completed activity coming in critical path??
Longest Path, literally means the same as it describes - the longest path from the Start of the Project to Finish of the Project. It DOES include completed activities.
Critical activities can be defined the way you want - it can be activities with less than certain amount of Total Float or it can be the longest path.
Which activities appear in critical path depends on how you set up your critical path filter. Again the filter can be either to select the activities in the longest path or to select activities with TF less than certain amount. If you select Longest path, then your filter will show the LONGEST PATH including completed activities.
Member for
23 years 8 monthsRE: Completed activity coming in critical path??
to Raviraj Bhedase,
The solution is remove the actual finish date from the field, make sure the % of completion is not equal to 100 and remaining duration is not equal to 0.
Any of the above 3 will cause the problem but they are input incorrectly only
Member for
18 yearsRE: Completed activity coming in critical path??
Well, Your suppose to remove the relationships(predecessors) of the completed activities so your critical path will start at Data Date. Right? Try...
Member for
18 years 5 monthsRE: Completed activity coming in critical path??
My dear friend,
But then whats d solution for pranabs query. OR i will say what has created the problem.
Member for
23 years 8 monthsRE: Completed activity coming in critical path??
Both critical path and longest path start on data date.
What is critical is by your defined value setting to total float.
Member for
18 years 5 monthsRE: Completed activity coming in critical path??
So, does it mean LONGEST PATH doesnt start on the data date.
Is it?
Member for
22 years 10 monthsRE: Completed activity coming in critical path??
Deb,
You apparently have the critical path defined as, "the longest path." If an activity on the longest path was completed out-of-sequence (before logically preceding work was complete,) then this completed activity remains on the longest path in order to show the continuity of the path.
Hope that this helps. Good luck!
Member for
18 years 9 monthsRE: Completed activity coming in critical path??
Hello Raviraj,
Checked it , data date is after the completion date , the only thing i noticed is that it is the preceding activity to the critical path.
regards
deb
Member for
18 years 5 monthsRE: Completed activity coming in critical path??
No Clue Deb,
In a updated program, having actual completion date less than data date, critical path dont show any completed activity.
plz check ur data date and make sure data date is greater activity completion date.
Cheers,