P5 Physical % Complete does not roll up

Member for

18 years 1 month

I have tested on my PC and it show curve correctly when tick on checkbox of Earned value curve.

You can show "Planned value cost" on activity table to see whether it have value.

Member for

18 years 1 month

Hi Donovan.

Unfortunately we still have not understood your request.

What window are you currently in to show histogram? Tracking or Activities.



Thanks

Member for

19 years 11 months

Thanks K D ,Really appreciate your help, will try and let you know,I also need to show a histogram with planned, actual & earned and scurves for the same in one profile,

my profile histogram shows my budget,baseline,and actual,but the scurves,I have the planned value labour units & earned value labour units ticked but is not showing,



Please help



Regards

Donovan

Member for

18 years 1 month

Hi buddy.



’Physical % complete’ is not rolled up, because it is a

discrete, user entered value assigned to an activity. Since

’Physical % Complete’ does not relate to the duration,

units or costs of the activity, there is no common

denominator to use for the summary



Workaround:



It is possible to configure the Activity’s ’Performance %

complete’ to equal the ’Physical % complete’.

Performance % complete can be rolled up to the summary

bands. However, to achieve this, the following three

statements need to be true:

1) The ’% Complete type’ of the activities must be

set to ’Physical % complete’.

2) The ’Technique for calculating performance %

Complete’ needs to be set to Activity % complete.

3) Finally, in order for the Performance %

Complete to be rolled up to the summary band(s),

costs need to be assigned to the activity. These

costs must also be present in the Primary baseline.



This solution derive from Primavera