Oracle Primavera - PM6 Member for 19 years 11 months Member for 19 years 11 months Submitted by Donovan Govender on Tue, 2007-10-16 04:56 Permalink RE: P5 CANT CHANGE E/S TO ACTUAL DATES Thanks Rony Member for 18 years 1 month Member for 18 years 1 month Submitted by Rony Roberto on Fri, 2007-10-12 04:16 Permalink RE: P5 CANT CHANGE E/S TO ACTUAL DATES Don, go to status, click the actual date,then put a value on the peercent complete. Regards, rony Log in or register to post comments
Member for 19 years 11 months Member for 19 years 11 months Submitted by Donovan Govender on Tue, 2007-10-16 04:56 Permalink RE: P5 CANT CHANGE E/S TO ACTUAL DATES Thanks Rony
Member for 18 years 1 month Member for 18 years 1 month Submitted by Rony Roberto on Fri, 2007-10-12 04:16 Permalink RE: P5 CANT CHANGE E/S TO ACTUAL DATES Don, go to status, click the actual date,then put a value on the peercent complete. Regards, rony
Member for
19 years 11 monthsRE: P5 CANT CHANGE E/S TO ACTUAL DATES
Thanks Rony
Member for
18 years 1 monthRE: P5 CANT CHANGE E/S TO ACTUAL DATES
Don,
go to status, click the actual date,then put a value on the peercent complete.